Hi Tommy,
Let me tell you my understanding of your situation, and please let me know if I'm on track or not.
You have created a work item type called "Test Case" that is part of your team project. You have created work items that are of type "Test Case" (as opposed to "Bug" or "Task"). You have executed a few tests and published the test results to the TFS server.
Have you done any linking between the work items created and the test results? If not, then the system wont know that those particular test results belong to that particular work item. You can create reports on test results using the warehouse, but unless the test result is linked to the work item, the system wont know that they are linked.
Thanks, Mauli |